Projects archive
Energy renovation of the Municipal Court building in Slavonski Brod (Trg pobjede 13)
KK.04.2.1.04.0354
Beneficiary: Ministry of Justice and Public Administration
The project aims towards energy renovation of the Municipal Court building in Slavonski Brod, to achieve savings of 79.95% in energy for heating, 89.27% in primary energy, modernize the appearance of the building and increase the quality of life and work in it along with a positive impact on the environment. The renovated building of the Municipal Court in Slavonski Brod will become a paradigmatic example of a successfully implemented practice that will be applied to the energy renovation of other buildings of the judicial and prison system, which are characterized by high energy consumption. The target group of this project are judges, state attorneys and deputy state attorneys, civil servants and employees in the judicial bodies of the Ministry of Justice and Public Administration and citizens.
Total project value: 9,037,106.13 HRK
Grant: 4,266,994.42 HRK
Grant Agreement date: 18 September 2018
Implementation period: 18 September 2018 – 18 March 2021
Contact: Mr Enes Sedić, enes.sedic@mpu.hr
www.strukturnifondovi.hr
The project was co-financed by the European Union from the European Regional Development Fund.
The contents of this web page are the sole responsibility of the Ministry of Justice and Public Administration.
Energy renovation of the Municipal Court building in Virovitica (Tomaša Masaryka 8)
KK.04.2.1.04.0663
Beneficiary: Ministry of Justice and Public Administration
The project aims towards energy renovation of the Municipal Court building in Virovitica, which would save energy for heating by 72.20 %, reduce CO2 emissions by 57.25 % annually, modernize the appearance of the building and increase the quality of life and work in it, with a positive impact on the environment.
Total project value: 4,762,537.11 HRK
Grant: 2,471,304.07 HRK
Grant Agreement date: 3 September 2019
Implementation period: 3 September 2019 – 23 February 2021
Contact: Mr Enes Sedić, enes.sedic@mpu.hr
www.strukturnifondovi.hr
The project is co-financed by the European Union under the European Regional Development Fund.
The contents of this web page are the sole responsibility of the Ministry of Justice and Public Administration.
Energy renovation of the Gospić Prison building (Senjskih žrtava 15)
KK.04.2.1.04.0664
Beneficiary: Ministry of Justice and Public Administration
The project aims towards energy renovation of the Gospić Prison building, to save 69.02% in energy for heating, 49.79% in primary energy, reduce CO2 emissions, modernize the appearance of the building and increase the quality of life and work in it, along with a positive impact on the environment.
Total project value: 1,413,752.55 HRK
Grant: 662,274.93 HRK
Grant Agreement date: 21 March 2019
Implementation period: 21 March 2019 – 22 February 2021
Contact: Mr Enes Sedić, enes.sedic@mpu.hr
www.strukturnifondovi.hr
Energy renovation of the County State Attorney's Office building in Osijek (Kapucinska 21)
KK.04.2.1.04.0665
Beneficiary: Ministry of Justice and Public Administration
The project aims towards energy renovation of the County State's Attorney's Office building in Osijek, to save 71.69% in energy for heating, 66.92% in primary energy, reduce CO2 emissions by 68.08% annually, modernize the appearance of the building and increase the quality of life and work in it, along with a positive impact on the environment.
Total project value: 4,157,739.34 HRK
Grant: 2,384,579.26 HRK
Grant Agreement date: 3 September 2019.
Implementation period: 3 September 2019 – 23 March 2021
Contact: Mr Enes Sedić, enes.sedic@mpu.hr
www.strukturnifondovi.hr