Upon completion of public procurement procedure, a contract for continued reconstruction works on Split Municipal Court building was signed in late October 2022.
The interior renovation started on 7 November 2022 and covers final construction craft and installation works.
The works are scheduled to be completed in six months, after which the building will be furnished and equipped.
The end of works and relocation of the Split Municipal Court to the new premises is planned for the final trimester of 2023.
The project is co-financed by Norway Grants.